This essay has been written and submitted by students and is not an example of our work. Please click this link to view samples of our professional work witten by our professional essay writers. Any opinions, findings, conclusions or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of EssayCompany.

A time scale specifies splits of time. A functional timescale

is generated by each procedure that enables dates to be

specifically allocated to events.

Milestone

A milestone t is an event that receives distinct attention. It is frequently incorrectly put at the end of a stage to mark the completion of a work package or phase.

In supplement to signalling the completion of a key deliverable, a milestone could additionally signify a vital decision or the derivation of a critical piece of data, which outlines or affects the upcoming of a project. In this sense, a milestone not merely signifies distance travelled (key periods in a project) but additionally indicates association of excursion as key decisions created at milestones could change the path across the undertaking plan.

"A milestone is a task of zero duration that shows an important achievement of a project. Milestones are a way of knowing how he project is advancing if you are not familiar with the tasks being executed. They have zero duration because they symbolize an achievement, a point of time in the project" www.community.claizen.com 15 dec 2010

Internal Milestones

Internal milestones of a project are very important and must be described clearly by the project management. Project manger should keep a close eye on the internal milestones to make sure every milestone has been achieved. The developer will be interested in major events and it is used by the project manager to monitor the progress of the system under development.

External Milestones

Some milestones relate to the outer world of a project and for which the project manager have o depend on external entities. E.g. external milestones can be requested by a customer for completion of a particular deliverable at a certain time.

Informal Milestones

Individuals in the project development team use informal milestones to observe their progress against the whole development project.

The timescales and milestones of my system are explained as follows

Buying /Acquiring a building for sales/training centre

First milestone of this project is to buy a building for my IT sales/training centre. It took us about two weeks to search for affordable premises

Buying Training Centre Equipment

My centre will not only be involved with computer sales but also raining for the staff that we have. This is an internal milestone and took about 12 days to buy and install these equipments.

Hire equipment

Options for hire of some equipment are necessary. Some equipment might be expensive to buy but easier to hire. In other cases it would be ideal to hire some equipment that would not be enquired for the long-term. 8 days were assigned to this milestone

Hire Buildings

For extra space instead of buying the building It is ideal to find allocations for hire. This could also be used for storage. 10 days were used for this milestone

Registration with government bodies

The organisation needs to register with government bodies to improve quality both for the training and sales sector. 7days were used in this milestone

Staff Hire

Hiring of staff was grouped in two stages. Those that were fully qualified and those that required training in the sales sector. 14 days were used for this milestone.

ISO Certificates

The company has to be registered with international standards. 20 days were used for this milestone

BSI Certificates

It is essential to get British standards for my IT sales and training centre. 20 days were used for this milestone

Opening

Opening is very important as it can automatically lead to good performance. Our vision is of "hit the ground running" when all the aspects are met timing will be very important. 5days will be used in this milestone

Task 2

Apply project planning and management tools to the system showing the following tools: Gantt chart, network diagram (e.g. EET, LAT, maximum span and total float) and show the critical path

Activity

Activity Name

Estimated

Time(days)

Dependency

1

Buying /Acquiring a building

14

-

2

Buying Training Centre Equipment

12

1

3

Hire equipment

8

1

4

Hire Buildings

10

1

5

Registration with government bodies

7

1

6

Staff Hire

14

4

7

ISO Certificates

20

5

8

BSI Certificates

20

5

9

Opening

5

-

LAT

Latest allowable time which specifies the latest time an activity may start in order to accomplish a task on time

Maximum span

Maximum span is the maximum time period that an activity has to be accomplished in

Therefore maximum span = LAT – EET

Total float

Total float is calculated as the maximum span minus the estimated duration. This is important when ascertaining the critical point within a project as activities have a total float zero are said to be on the critical path

Activity

Estimated duration

Maximum span

Total float

1

14

14

0

2

12

14

2

3

8

15

7

4

10

10

0

5

7

9

2

6

14

20

6

7

20

20

0

8

20

20

0

9

5

5

0

Critical path

Critical path is the critical area of the project. If we have any delay in the activities of the critical project, path area then the project will be delayed.

The diagram below is the critical path of my project

TASK 3

Discuss system documentation tools: quality assurance teams –quality review meetings – and cost estimate

Quality assurance

Quality assurance (QA) refers to the projected and systematic activity requested in a quality arrangement so that quality necessities for a product or service will be fulfilled. It’s the systematic measurement, analogy alongside an average, monitoring of procedures and an associated feedback loop that confers error prevention. This can be contrasted alongside quality control, which is concentrated on process outputs.

In developing products and services, quality assurance is any systematic process of checking to see whether a product or service being developed is meeting specified requirements. Many companies have a separate department devoted to quality assurance. A quality assurance system is said to increase customer confidence and a company's credibility, to improve work processes and efficiency, and to enable a company to better compete with others (http://searchsoftwarequality.techtarget.com/definition/quality-assurance)

Quality assurance team

The QA team aid mechanisms, gadgets and leadership to perfom better. Their target is for managers to come to be better leaders. The act of a leader is very different from a manager. They are coaches. Coaches intuitively develop supplementary people, endeavouring to aid them and help accomplish their maximum potential; police impose and enforce rules. It is their job to catch people after they are acting something wrong. It can be tough to discover this believed lacking the aid of a quality assurance team, but integral to accomplished success and profitability.

A QA develops the true leader so that they may know how to address problems, resulting in solutions that are a "win-win" for everyone concerned. (http://www.qaap.net)

In my project we have made sure that we do not compromise over quality. For this purpose there was a special team to keep check and balance the development process. Their main job was to monitor that project and make sure that all the quality procedures and equipments is used and tasks finished within the given timeframe

Quality review meetings

Purpose:

The purpose intention of this procedure is to delineate the methods utilized to study the Quality Arrangement that is in operation.

Scope:

This procedure applies to all Management Review Meetings, encompassing their associated documentation.

Definition

Management Review: this is a structured meeting that should take place at usual intervals to debate the working of the quality arrangement of the EBME Department andtake appropriate action to correct it after necessary.

Responsibilities

the Facilities Manager or the EBME Manager has the responsibility to conduct regular Management Review Meetings. It is the obligation of the Quality Assurance Manager to safeguard that this procedure is carried out.

Objectives of mangement review meetings

The objectives of the Management Review are:-

To institute that the Quality Assurance system is accomplished and followed the anticipated aftermath, conforming to the standard, and working in accordance alongside the instituted operating Procedures.

To expose irregularities or defects in the System, recognize flaws and create recommendations for continual improvement.

To study the effectiveness of preceding corrective actions encompassing those connected to subcontractor and supplier presentation.

Review of the adequacy and suitability of the Quality Assurance System to be used for current and future operations.

Review each complaints consented, recognize the cause and advice corrective actions if needed including client feedback.

Review the discovering of inner / external audits and recognize each span of recurring problems.

Review the reports of non-conformities and evaluate trend information.

To study training requirements. Analyse all the above for trends and create appropriate improvements

"The central phase of the quality review process is the review meeting itself. During the review meeting the emphasis should be on error detection, in line with the criteria, and only limited discussion of corrective action should occur. It is important that 'personalities' and 'politics' are kept out of the review - in particular it is essential that the review remains focused on the review item and not on the presenter. For reviews that are 'complete' the action list tasks are allocated along with designated reviewers, to verify that the work is done. If the review ends abnormally it should be deemed 'incomplete'. Error lists and copies of annotated products should be brought to the meeting by each reviewer, or sent to the chairman before the meeting if the reviewer is unable to attend. If the review is deemed 'complete', then the chairman should forward the follow-up action list and all copies of the annotated product to the presenter together these represent all of the errors identified. The chairman should also distribute copies of the result notification to the presenter and the reviewers. A project exception report should be raised for any errors detected in non-review items"

http://www.getahead.uk.com/gwpm29-quality-reviews.htm

Cost estimate

"Approximation of the probable total cost of a product, program or a project computed on the basis of available information" www.businessdictionary.com 5 Dec 2010

Cost estimating is one of the most vital steps in project management. The bass line of various stages of a development project is established in a cost estimate A cost estimate at a given period of project development embodies a forecast endowed by the cost engineer or estimator on the basis of obtainable data. According to the American Association of cost Engineers, cost engineering is described as that span of engineering exercise whereas engineering judgment and experience are utilized in the request of logical principles and methods to the problem of cost estimation, cost control and profitability.

The magnitude of every single of the cost components depends on the nature, location and size of the project as well as the management company, amid countless considerations. The owner is interested in accomplished the lowest possible overall project cost that is consistent alongside its investment objectives

Most construction budgets have an allowance for contingencies or unexpected costs occurring across construction. This contingency number could be included inside every single price item or be included in a single group of assembly contingency. The number of contingency is established on past experience and the anticipated difficulty of a particular assembly undertaking

. For example, my IT sales business will looks at these five different areas:

Design development changes,

Schedule adjustments,

General administration changes (such as wage rates),

Differing site conditions for those expected, and

Third party requirements imposed during construction, such as new permits.

Cost estimate of my project

TASK

ESTIMATED COST

Buying /Acquiring a building

£25,000

Buying Training Centre Equipment

35,000

Hire equipment

15,000

Hire Buildings

10,000

Registration with government bodies

2500

Staff Hire

12,000

ISO Certificates

2000

BSI Certificates

2500

Opening

1800

TOTAL ESTIMATED COST

105800



rev

Our Service Portfolio

jb

Want To Place An Order Quickly?

Then shoot us a message on Whatsapp, WeChat or Gmail. We are available 24/7 to assist you.

whatsapp

Do not panic, you are at the right place

jb

Visit Our essay writting help page to get all the details and guidence on availing our assiatance service.

Get 20% Discount, Now
£19 £14/ Per Page
14 days delivery time

Our writting assistance service is undoubtedly one of the most affordable writting assistance services and we have highly qualified professionls to help you with your work. So what are you waiting for, click below to order now.

Get An Instant Quote

ORDER TODAY!

Our experts are ready to assist you, call us to get a free quote or order now to get succeed in your academics writing.

Get a Free Quote Order Now