Cost Overrun Project At The Others Countries

Print   

02 Nov 2017

Disclaimer:
This essay has been written and submitted by students and is not an example of our work. Please click this link to view samples of our professional work witten by our professional essay writers. Any opinions, findings, conclusions or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of EssayCompany.

CHAPTER 2

LITERATURE REVIEW

This literature review chapter will focuses on the discussion related to gross domestic product, economic census, principal statistic of construction industry, statistic of Bumiputera contractors and statistic of cost overrun projects.

Gross Domestic Product

One of the impact of cost overrun project is retards the development of construction industry. Delays (time overrun) and cost overrun are costly and often result in disputes and claims, impair the feasibility for project owners, and retard the development of the construction industry (Battaineh, 2002). Construction industry is one part that contribute in the growth of the gross domestic product of our country. What is gross domestic product? Gross domestic product(GDP) is an indicator to detect the performance of the economy growth of country either it is increasing or decreasing from the previous year. It also uses to know the pattern of economy's growth in certain period. As example, the year to year GDP is 5%, so that means economy is increase 5% from the previous year.

The calculation of GDP is very complicated, so it always be done by the professional economist. Basically, the GDP is addition of every economy's activities such as agriculture, mining and quarrying, construction, manufacturing, services, duties, and etc. There were two ways of measurement of GDP; first is by plus what was every people earning for the year which is known as income approach, second is what is every people spent which is known as expenditure method. The difference of this two method is almost same after total up.

This is the ways how this two method of GDP is calculated:

By income(various forms of income received by the primary factors of production) (Stanford, 2008):

GDP = wages plus profit

GDP = W + II

By expenditure method (the output of different ways is "buy" (Stanford, 2008):

GDP = application + government production + investment + net exports

GDP = C + G + I + (X � M)

Malaysia practice growing and relatively open economy (Yusop, 2009). Because of this, construction had the impact of decrease in GDP in year 1997 during Asian Financial crisis because as we know construction also is included in the GDP of Malaysia as it contribute to the growth of Malaysia's economy.

Table 1 Gross Domestic Product By Kind of Economic Activity

Source of Ministry of Finance Malaysia 2013

As we can see from the table, the average GDP for construction sector from year 2009 till 2012 is 8.1%. From the table also we can see that the growth of construction industry from the year 2009 till 2011 decrease by 1.6% before it rise to 15.5% at the year 2012. From this data show that the growth of construction industry can give the impact to the GDP.

Table 2: Percentage Distribution of Economic Activity by State at Constant Price 2000 Year 2010

Gross Domestic Product (GDP) by State, 2010 (Updated: 17/10/2011)

Table 2 shows that the percentage of GDP activity for every state in Malaysia. Selangor state rank first for the construction industry among every state. That�s means the construction activities in Selangor was the most vigorous and got high demand from clients and developers.

As we can imagine, the GDP growth give the impact to every activities and vice versa. If the GDP of construction industry decrease so that the total GDP of our country even other activities show increasing. Cost overrun is one of the factor that can decrease the percentage of construction industry in GDP. By that, cost overrun should avoid as far as possible.

2.1 Cost Overrun

Cost overrun happens when the actual cost of project is more than estimated cost. As example, one client wanted to build a residential house and the estimated cost is RM50,000. Then, the project is said to be overrun of 10% in cost from expected cost when the project finish the total is RM 55,000. In this case, the client had to pay RM5,000 more and he is not get profit from that but the worst is he lost that money.

2.1.1 Cost overrun project at the others countries

2.1.1.1 The Big Dig

One of the largest and the most cost overrun project in United State history is The Big Dig which was executed at the Central Artery, Boston. The purpose of this project was to change six lanes with eight to ten lanes of Central Artery with an underground road. This project was to be said as one of the most hard infrastructure project that ever attempted because it includes the constructed of other roads and tunnel and major bridges (Silverman,n.d).The Big Dig project started from the end of the year 1991 and was finished completely on Dec. 31, 2007. This project is said to overrun in cost up to $ 14.8 billion from $ 2.6 billion which was the initial cost estimated (LeBlanc, 2007). However, with the interest borrowed from fund, it's cost completely rise up to $22 billion and had to pay up to year 2038 (Murphy, 2008).

One of the problem that caused this project exceed budget was came from it's design. The mistakes and poor decision in Bechtle's design contribute to $1.6 billion in cost overrun. This chart show the cost overrun in every section in the Bechtle's design (Butler,n.d).

2.1.1.2 The 2010 FIFA World Cup Stadia in South Africa

This project is among a big project that ever occurred in South Africa because it involved the construction of ten stadia across the country. When the construction of all the stadia finish, no one ever talk about the cost until the Minister of Finance was cited in Africa Report (Ballong, 2010) our government had been dealt with the cost exceed budget case and the budget for all the stadia is USD 267 million in deficit. Table 3 provided the summary of the initial and the final cost of some stadia (2010 SWC stadium costs and updates).

Table 3. estimated versus indicated final cost of ten FIFA 2010 stadia

Baloyi and Becker(2011) has stated in their research that the increase in material cost is the main cause that increase of total budgeted cost of all the stadia. The other factors that had been ranked by their contribute are as shown in the table 4.

Table 4. ranking of the factors cause the cost overrun at stadia

Cost overrun factors RII Rank Category

Increase in material cost 0.79 1 External

Inaccurate material estimates 0.60 2 Client

Shortage of skilled labour 0.58 3 Contractor

Client�s late contract award 0.56 4 Client

Project complexity 0.55 5 External

Increase in labour cost 0.54 6 External

Inaccurate quantity take-off 0.53 7 Client

Difference between selected bid and the consultants� estimate 0.52 8 Client

Change orders by client during construction 0.51 9 Client

Shortage of manpower 0.51 9 External

From the table we can see that the client's category was the major factor contribute to make the cost of construction of all the stadia overrun in the top 10 ranking made follow by external and lastly contractor category. Even though client is major contribute, but the critical factor was increase in material cost which was under external factor.

2.1.1 Cost overrun project in Malaysia

2.2 Factors influence cost overrun

Some researchers debated that cost overrun is one of the factor from the project delayed problem. The responsibility of construction delayed is reflected by contractor either in time or cost to complete the project (Ahmed, 2003).

Previous research has attempted discover reasons for the disparity between the tender sum and the final account. This section identifies the factors that influence cost overruns. Four factors were identified from the existing research findings Morris et al (1990), Kaming et al (1997) and Chimwaso (2001). These are; design changes, inadequate planning, unpredictable weather conditions; and fluctuations in the cost of building materials.

To broaden the investigation it was decided to complement the above list of factors with other factors gleaned from the final account reports. These were compared with the factors from the existing research findings, and a final list of 18 factors was prepared. Those were then divided into two groups of seven critical factors and nine other factors, which are usually ignored, but perceived to be of equal significance ( Chimwaso; 2001).

List of critical factors

1.Incomplete design at the time of tender.

2.Additional work at owner's request.

3.Changes in owner's brief.

4.Lack of cost monitoring/planning during post-and-pre contract stages.

5.Site/poor soil conditions.

6.Adjustment of prime cost and provisional sums.

7.Re measurement of provisional works.

8.Logistics due to site location.

9.Lack of cost reports during construction stage.

List of other factors, which are usually ignored

1.Delays in issuing information to the contractor during construction in delays.

2.Technical omissions at design stage.

3.Contractual claims, such as, extension of time with cost claims.

4.Improvements to standard drawings during construction stage.

5.Indecision by the supervising team in dealing with the contractor's queries in delays.

6.Delays in costing variations and additional works.

7.Omissions and errors in the bills of quantities.

8.Ignoring items with abnormal rates during tender evaluation, especially items with

provisional quantities.

9.Some tendering manoeuvres by contractors, such as front-loading of rates.

The prime variables of cost overruns have been commonly identified as: unpredictable weather, inflationary material cost, inaccurate materials estimates, complexity of project, contractor�s lack of geographical experience, contractor�s lack of project type experience, and non-familiarity with local regulations (Kaming et al 1997).

Morris (1990) studied the factors influencing cost overruns in public sector projects, he found that Escalation in costs is attributable partly to the fact that the original estimates were prepared at the then current prices, and partly to delays which enhance the effect of inflation and to direct escalation in costs arising out of change in scope, errors etc. Based on certain assumptions with regard to the pace of expenditure on projects Morris have roughly computed that for the 133 projects which were studied only about 25 to 30% of the cost increase can be attributed to inflation. The remaining 70 to 75% has to be explained in terms of delays, inefficiencies, scope changes, changes in statutory levies, variations in exchange rates and to the combined effect of these factors with inflation.



rev

Our Service Portfolio

jb

Want To Place An Order Quickly?

Then shoot us a message on Whatsapp, WeChat or Gmail. We are available 24/7 to assist you.

whatsapp

Do not panic, you are at the right place

jb

Visit Our essay writting help page to get all the details and guidence on availing our assiatance service.

Get 20% Discount, Now
£19 £14/ Per Page
14 days delivery time

Our writting assistance service is undoubtedly one of the most affordable writting assistance services and we have highly qualified professionls to help you with your work. So what are you waiting for, click below to order now.

Get An Instant Quote

ORDER TODAY!

Our experts are ready to assist you, call us to get a free quote or order now to get succeed in your academics writing.

Get a Free Quote Order Now