Design And Build A Construction

Print   

02 Nov 2017

Disclaimer:
This essay has been written and submitted by students and is not an example of our work. Please click this link to view samples of our professional work witten by our professional essay writers. Any opinions, findings, conclusions or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of EssayCompany.

I Project Introductions 2

II Project Scope 2

III Project Delivery Systems 2

IV Estimations 3

1 Budget Cost Estimations 3

2 Time Estimations 5

3 Project Network 7

4 Critical Task 8

5 Work Breakdown structure 9

6 Mile Stone 10

V Project Risks 11

VI Event Promotions 12

VII Recommendations 12

VIII Conclusions 12

IX Reference 13

Project Introduction

Our project is the Design and build a construction of a single user guard house at empty land in fishery port road for the future usage. This document is discuss about the project, design and functional components, Project delivery system, Project schedule, and create the summary , cast evaluation, work break down structure, project risks and other discussion and recommendation for the project.

Project Scope

For the project have approved from necessary authorities, It is build for a developer’s empty land for future usage. The size of building is 100 sq.m. fully computerized and air conditioned. Very soon there going to construct a single user warehouse building. Design & Build project , which involves designing the house scheduling and figuring out what are the materials needed, ordering or purchasing the materials, and putting together the various parts. Some of these tasks depend on the others, some must be scheduled, some take labour, etc

Project Delivery systems

The original project was arranged to be a design & build with project manager at risk. Through conservations with involved parties, the project has morphed in to a more traditional Design bid build delivery. The original delivery method was chosen to allow the project to begin development prior to completion on time and satisfy the wants from the owner in the time desired created a scenario that would be best fit by the design build with project manager at risk delivery method.

Estimations

The project estimation like Budget cost estimations ( Finance Estimations), Time estimation, for the whole project and also work estimation such as project network and work breakdown structure.

Budget Cost Estimations

Total cost Estimation for our project is $ 37, 874.00, Its based on this assumption and calculation from the software . We assume for the contractor each and every stage. The fallowing components are consider for cost estimations:

Components:

Pre Constructions

Barricade the Site

Cleaning and Cable detections

Foundations

General Excavations

Footings

Ground Beams

Super Structure

Columns

Beam & Roof Slab

Brick Work

Finishing works

Wooden Works

Plastering Works

Flooring Works

M&E Works

Painting Works

Hand Over

Rectifications works

Fig 1 : Budget Report

Fig 1.1 Cash Flow Report

Fig 1.2: Earned Value Report

Time Estimation

Try to start the project as soon as possible. Our estimated starting date is Second week of January 2013, ( 14/ 01/2013 ) And Completed on March 2013, ( 22/3/13 ) total 50 Days of project. The details of following deliverable stages are listed below:

Deliverable stages:

Pre construction – 3 Days ( 14/1/13 – 16/1/13 )

Foundations – 12 Days ( 17/1/13 – 1/2/13 )

Super Structure – 14 Days ( 4/2/13 – 21/2/13 )

Finishing work – 18 Days ( 22/2/13 – 19/3/13 )

Hand Over – 3 Days ( 20/3/13 – 22/3/13 )

Total Days – 50 Days ( 14/1/13 – 22/3/13 )

Fig 2: Project schedule ( For Time Estimations )

Fig 3: Project schedule on Gantt chart ( For Time Estimations )

Fig 4: Resource Usage report

Project Networks

Our project start with the pre construction and going to foundations , super structure, finishing works and hand over. Each activity have sub or miner activity.

Pre construction - Barricade the Site , Cleaning & Cable detections

Foundations - General Excavations, Footings & Ground beams

Super Structure – Columns, Beams & Roof slab & Brick Works

Finishing Work – Wooden work, Plastering , Flooring, M&E and Painting

Hand Over – Inspection & Rectification works and Hand over

Fig 5: Project Network Diagram

Critical Task

Fig 6 : Critical Task Chart

Fig 7: Critical Task Report

Work Breakdown structure ( WBS)

Fig 8: Work Breakdown Structure

Fig 9: Resource work Summary Report

Mile Stone

Mile stone = Deliverable of stages in the Projects

Pre Construction :

Completion of Pre construction is the first deliverable stage of our project. Just stop this stage and review all the process its sub activity . We achieve this mile stone on 16 Jan 2013

Foundation :

Completion of Pre construction is the second deliverable stage of our project. Just stop this stage and review all the process its sub activity . We achieve this mile stone on 1 Feb 2013.

Super Structure :

Completion of Pre construction is the third deliverable stage of our project. Just stop this stage and review all the process its sub activity . We achieve this mile stone on 21 Feb 2013.

Finishing Works :

Completion of Pre construction is the fourth deliverable stage of our project. Just stop this stage and review all the process its sub activity . We achieve this mile stone on 19 Mar 2013.

Hand Over :

Completion of Pre construction is the fifth and last deliverable stage of our project. Just stop this stage and review all the process its sub activity . We achieve this mile stone on 22 Mar 2013.

Project Risks

Our project facing some the risk related cost, time, quality, environmental and safety. We discuss about the fallowing risks stated below:

Tight project schedule

Design various

Variations by the client

Unsuitable construction program planning

Occurrence of dispute

Price inflation of construction materials

Excessive approval procedure in administrative authorities

Incomplete approval and other document

Incomplete or inaccurate cost estimate

Inadequate program scheduling

High performance or quality expectations

Variations of construction program

Low management competency of subcontractors

Unavailability of sufficient amount of skilled labour

Lack of coordination between project participants

Insufficient site information ( soil test and survey report )

Serious noise pollution caused by construction

General safety accident occurrence

Event promotion

Event promotions is encourage the total manpower of the project It is general safety champions award for the worker and supervisor, who work with in the safety regulations for the maintain the safe working environment for the whole period of the project.

The event conducted on 22nd March, 2013 at the site assembly area.

Recommendation

Project Schedule : To complete the project within time must be start the project on the date 14/1/2013. Maintain the target time to complete each task. If not able to complete the then using the feeder buffer period to complete the task within the time.

Critical Task : Our project have a lot of critical task have to do. When start the critical task concentrate the project in full awareness. Task are try to crush if not able to crush then maintain the time and do not reduce the manpower and machineries.

Budget : When order any type of rental machineries , try to complete the work in most priority basics. Must be plan the work schedule for the machineries and keep monitoring for ensure complete the task within time and budget limits. Try to avoid unnecessary overtime payment for the workers and supervisor due to fallow up schedule.

Risks: Identify the all the type of the risk when carry out our project, then try to eliminate the impacts of risks. If not possible to reduce the impacts the arrange all the precaution methods to protect the project delay.

Conclusions

Finally we are in the finishing stage of this document, we discuss about the project , schedule , budget, risks , other construction related and non construction related matters to carry out the project to getting a successful completions. We work out from the MS project software getting Gantt chart, cost estimations , critical task, network diagram, mile stone, project summary to complete the project. Also we give some of the recommendations on project schedule, critical task, budget and risks of the project to improve the productivity of project manager on their project.



rev

Our Service Portfolio

jb

Want To Place An Order Quickly?

Then shoot us a message on Whatsapp, WeChat or Gmail. We are available 24/7 to assist you.

whatsapp

Do not panic, you are at the right place

jb

Visit Our essay writting help page to get all the details and guidence on availing our assiatance service.

Get 20% Discount, Now
£19 £14/ Per Page
14 days delivery time

Our writting assistance service is undoubtedly one of the most affordable writting assistance services and we have highly qualified professionls to help you with your work. So what are you waiting for, click below to order now.

Get An Instant Quote

ORDER TODAY!

Our experts are ready to assist you, call us to get a free quote or order now to get succeed in your academics writing.

Get a Free Quote Order Now